EnergyConnect begins power transmission in the west
EnergyConnect has reached a major milestone, with electricity now flowing for the first time through its western section, marking a new chapter in Australia’s energy transformation.
EnergyConnect has reached a major milestone, with electricity now flowing for the first time through its western section, marking a new chapter in Australia’s energy transformation.
Australia’s largest transmission project EnergyConnect has connected the first section of the new Buronga substation in south-western New South Wales to South Australia.
Transgrid and its construction partner Elecnor Australia have finished the construction of Line 1.
ElectraNet announced that the South Australian portion of the EnergyConnect project has neared completion.
Transgrid has installed first batch of steel towers within a power transmission project to interconnect New South Wales, South Australia and Victoria.
Rigorous performance testing of the transformers for Australian $1.8 B-worth EnergyConnect project is currently underway in South Korea.