Baghdad, Iraq: Iraqi Ministry of Electricity (MoE) and GE Power’s Grid Solutions business celebrated the energization of the Baghdad West North substation. Located about 35 kilometers away from the city, the substation can help connect up to 1,000 megawatts (MW) to the national grid, decreasing bottlenecks and increasing the hours of available power.

H.E. Luay Al-Khatteeb, Minister of Electricity, said, “The Iraqi Ministry of Electricity is seeking to provide reliable, uninterrupted power across the country. The opening of the Baghdad West North substation reflects our efforts to achieve this goal. The substation will play a critical role in helping to deliver much-needed power, especially in the upcoming summer months.” 

GE’s scope of work for the turnkey 400/132/11 kilovolt (kV) gas insulated substation project included the design, equipment manufacturing, site delivery, erection, testing & commissioning, and training of personnel. The project’s construction, erection, commissioning, and testing was completed by GE Iraqi engineers in collaboration with local Iraqi subcontractors.

The facility can feed 132 kV substations at Kadhmiya, Al Shualla and Al Sabbeaat, as well as another five substations that are planned to be developed in the future and helps connect power from the Basmaya Power Plant, Taji Gas Power Plant and mobile gas power plants to the national grid. 

Following the agreement for the Baghdad West North substation, GE also signed a US$400 million agreement to develop and rehabilitate 14 additional electric substations, and to supply critical equipment such as transformers, circuit breakers and other related equipment.

The substations will connect power plants spread across the governorates of Ninawa, Salah Al Din, Al Anbar, Karbala, Baghdad, Qadisiyyah and Basra to the national grid. Several of the locations, in conflict-affected areas, have an immediate need of reliable power infrastructure.